Call Us Today:

Inland revenue offices, Crescent Centre, Bristol

}?>

Lift removal and installation

Budget: £120,000

Duration: 4 months

This project included the removal of the existing 4 lifts and replaced it with an OTIS Gen2 lift. We also had to complete alterations to the marble work and the installation of new stainless steel architraves. All works were carried out in out-of-hours so as to limit disruption to the offices.

Downside Abbey Monastery

}?>

Lift removal/installation, construction

Budget: £40,000

Duration: 14 weeks

CBES lift engineering department removed and installed a lift shaft in a historic grade 1 listed building. This was a complicated and delicate project, as we had to ensure the old timbers finishers were retained. Also the new timbers had to be in keeping with the character of the building. Fire proofing was also carried out to comply with safety regulations. This project had to be extremely well planned, as it had to be completed successfully on a tight timescale.

client industries: