ARLA foods, Swindon

}?>

Electrical installation

Budget: £600,000

Duration: 9 months

The design. installation and testing of new electrical & mechanical systems for the new butter making plants and westbury dairies. We used stainless steel containment for a clean area as it was a food environment. Technical work was completed while the plant remained in operation.

Nisbets Kitchenware, Bristol

}?>

Construction and refurbishment, electrical installation

Budget: £140,000

Duration: 4 months.

This project was combined two of our three key divisions:  construction end electrical. The premise was to complete a building alteration to the existing building and the construction of a new reception area. Further to this we completed an installation of new electrics and air conditioning.